A Brief Discussion on Construction Techniques for Municipal Road and Pipeline Projects


Release Date:

2018-10-19

Discussion on construction techniques for municipal road and pipeline projects is of great importance; only through the exchange of technical knowledge can projects be completed more efficiently, and every construction detail can be refined—both of which are crucial. The editors of the Construction Network will now introduce this topic to you.
 
1 Construction Surveying
 
Construction surveying is highly technical and runs throughout the entire construction project; it must be carried out by dedicated technical personnel to ensure timeliness and accuracy. At the same time, to guarantee that every construction process can withstand error-free digital verification, we are continually raising the requirements for measurement accuracy in self-inspection and self-testing procedures.
 
2 Pipeline Laying and Construction Techniques
 
2.1 Demolition of Urban Roads
 
To ensure the safety of the project and the quality of the roadbed, the roadway where the pipeline is to be laid shall first be surveyed and staked out to establish the pipeline’s centerline, mark the start and end points, and determine the locations of the pipe burial depth, inspection chambers, and stormwater inlets. The asphalt surface layer and subgrade base course shall then be removed using an excavator, with a backhoe excavator employed to survey and excavate along the installation alignment. During earthmoving and stockpiling, the soil must be kept at least 3.0 meters away from the edge of the pipeline excavation pit, and the height of the stockpile must not exceed 3.0 meters.
 
2.2 Trench Excavation and Shoring
 
During trench excavation, mark the excavation line with paint based on the calculated excavation width, and use a cutting machine to sever the asphalt pavement layer and the concrete surface layer. Ensure that slope grading is scientifically sound, safe, and cost-effective, thereby guaranteeing construction safety and unobstructed access to the subgrade. During excavation, use an excavator to remove the crushed asphalt and road debris from the pavement surface; moreover, after excavating a specified distance, rigorously measure and verify the bottom elevation of the trench. Special attention must be paid to avoid over-excavation at the trench bottom; if over-excavation occurs, the affected area must be immediately backfilled and compacted. It is strictly prohibited for water to accumulate at the lowest point of the trench bottom, and it is also strictly forbidden to use humus soil, garbage soil, sludge, or similar materials during compaction.
 
2.3 Pipeline Foundation Construction and Installation
 
The foundation for stormwater drainage pipes may be constructed as either a 120° or 180° concrete footing, with a concrete grade of not less than 10 MPa. All concrete used in the project is mixed on-site and transported by dump trucks; upon arrival at the placement location, it is conveyed down into the excavation using chutes, followed by compaction with an immersion vibrator. Prior to pipe installation, the quality of each pipe must be re-inspected and verified. Once confirmed to be compliant, 12-ton truck-mounted cranes are employed for lifting and hoisting, with careful handling—lifting and setting down gently—to prevent damage. Lighter pipes may be manually handled and transported. For spigot-and-socket stormwater pipes, cement-sand mortar joints shall be used, with a joint width of 12 cm and a joint thickness of 3 cm.
 
2.4 Manhole Construction
 
During inspection well construction, surveying must be carried out first, followed by the placement of a 10 MPa concrete foundation. Masonry of the well wall may commence only after the concrete has attained a strength of 2.5 MPa. Upon completion of the masonry work, the inner and outer surfaces of the inspection well shall be plastered with a 1:2.5 cement mortar to a thickness of 20 mm, with the finish required to be smooth and well-pressed; hollows and cracks are not permitted.
 
2.5 Stormwater Inlet Construction
 
During the construction of stormwater inlets, surveying and layout shall be carried out first, followed by the placement of a 10 MPa concrete foundation. The well walls shall then be constructed using manual string-line alignment, and the inner surfaces shall be finished with a 1:2.5 cement mortar screed. The inlet grate ring shall be installed on a stable bed of mortar. Finally, curb stones shall be laid and cast-iron grates shall be placed.
 
3 Construction Technology for Water Supply Pipeline Engineering Projects
 
The most critical component of municipal road pipeline construction is the water supply pipeline project, which has incorporated several distinctive technologies and construction methods in practical applications.
 
(1) First, survey and establish the centerlines of each branch pipeline, driving steel or wooden stakes at these locations to serve as fixed reference points for the elevation and centerline of the water supply pipeline.
 
(2) Based on the surveyed centerline, trenching shall be carried out using a trenching machine, with manual labor employed in conjunction to ensure proper coordination. During excavation, the slope ratio of the pipe trench shall be determined according to the pipe diameter and the soil characteristics of the construction site. In this project, mechanical excavation will be used; a sufficient layer of soil—typically 15–25 cm—shall be left at the bottom of the trench to be subsequently removed by hand until the design elevation is reached, thereby ensuring that the underlying soil layer remains undisturbed.
 
(3) Installation and construction of prestressed reinforced concrete pipes. First, the installation sequence for this project is as follows: pipe alignment, pipe lowering, cleaning of the pipe bore and pipe ends, cleaning of the rubber gasket, installation of the rubber gasket, preliminary alignment and positioning, jacking and spigot-and-socket connection, verification of the centerline and elevation, inspection of the rubber gasket position using a probe gauge, and final securing of the pipe. Second, the individual pipe sections are installed. In this project, a 12-ton crane is used to lift each pipe section and place it inside the pipe trench, with installation carried out in accordance with the previously surveyed centerline. During installation, the first step is to apply lubricant to the tail end of the pipe and to the interior of the spigot-and-socket joint, after which the pipe is inserted into the spigot. When installing the pipe sections, the spigot of the first section is positioned forward, and once the tail end of the second section is aligned with the spigot, a 3-ton horizontal tensioning device is used to steadily push the section into its designated position, ensuring proper sealing by the rubber gasket. After completing the installation of the first and second pipe sections, the tensioning device is temporarily released, and the steel wire rope securing the second section is loosened; the tensioning device is then re-secured to the first section, and the third pipe section is installed following the same procedure, continuing in this sequential manner.
 
4. Installation Techniques for Pipeline Steel Pipes
 
The installation of pipeline steel pipes is a critical step throughout the entire municipal road pipeline construction process. First, the quality of the pipe material must be ensured; in accordance with relevant codes and standards, internal anti-corrosion and anti-rust treatments shall be applied, including spraying cement slurry inside the pipe, applying anti-rust oil to the outer wall, and performing anti-corrosion treatment with epoxy asphalt. Steel pipes are then laid out along the surveyed centerline, tack-welded for positioning, and joined at the seams. Pipeline steel pipe installation is carried out according to the design drawings; after verifying tight sealing, a water-tightness test is conducted, followed by flushing and disinfection of the pipeline.
 
5 Conclusion
 
Drawing on practical experience in the construction of municipal road pipeline projects, this paper identifies common technical challenges in such projects and proposes corresponding solutions. It places particular emphasis on installation techniques for pipeline works, offering valuable guidance for enhancing the quality of municipal road pipeline construction.