Discussion on Key Points of Construction Surveying for Municipal Engineering Projects


Release Date:

2019-09-18

The construction of municipal engineering projects is primarily divided into two main categories: road works and drainage works. Due to the surrounding construction environment and the typically urban locations of such projects, surveying for municipal engineering is often complex and subject to significant variability.

The construction of municipal engineering projects is primarily divided into two main components: road works and drainage works. Due to the typical urban setting and the surrounding construction environment, municipal surveying is often highly complex and subject to significant variability. Therefore, during surveying, it is essential to base the construction plan on the construction drawings and take into account the existing buildings and underground utility lines in the vicinity. Drawing on many years of construction experience, this paper will now provide a detailed discussion of municipal construction surveying, dividing it into two distinct sections: road construction surveying and drainage construction surveying.
 
1 Road Construction Surveying
 
1.1 Determination of Construction Edge Piles
 
After the commencement of road construction, the stakeout points provided by the design institute for the centerline will be destroyed due to road excavation. Therefore, two rows of construction sideline stakes are typically set out on either side of the road centerline, parallel to it (and, if existing structures are present on both sides of the road, these structures may also be marked). Each sideline stake is labeled with the distance from the road centerline, as well as the stake number and elevation (with the elevation expressed as a vertical offset relative to the design road centerline elevation).
 
1.2 Longitudinal and Transverse Profile Survey
 
By conducting centerline surveys, setting out sideline stakes, and arranging control coordinates and benchmark points, longitudinal and transverse profile surveys can be carried out (currently, the Road Earthwork Quantity Calculation Expert software is commonly used). The primary purpose of these surveys is to calculate earthwork volumes; therefore, upon completion of the longitudinal and transverse profile surveys, the survey results must be verified against the quantities specified in the design drawings. For discrepancies that are minor after comparison with the design drawings, the original quantities shall prevail; however, if the differences are substantial, the supervising engineer must be notified immediately for verification and subsequent adjustment. Earthwork verification must be conducted prior to the commencement of road construction. If the actual on-site measured earthwork volume differs from the design volume, a request for re-measurement by the supervisor should also be submitted before construction begins. In some projects, contractors only submit a claim to the supervisor after pipeline trench excavation, alleging a discrepancy between the on-site measured earthwork volume and the design volume and requesting re-measurement and additional change orders; under normal circumstances, the supervisor will reject such requests. Therefore, it is crucial to ensure the timeliness of this work. It should also be noted that, during longitudinal and transverse profile surveys, in addition to meeting the minimum point requirements stipulated in the relevant codes, it is advisable to add extra survey points in areas where earthwork volumes are likely to increase or decrease, such as steep slopes or depressions.
 
1.3 Subgrade Engineering Layout
 
During construction, first establish the subgrade center elevation and edge stakes on site in accordance with the design elevations shown on the longitudinal profile and the standard cross-section drawings (this step was already completed when the construction stakes were initially driven). These stakes serve as reference lines for the contract workers during construction. While the contract workers are laying out the alignment using these lines, surveyors must continuously recheck the accuracy of the stakeout points to prevent errors such as misalignment of the string lines, which could lead to rework. It is also essential to use a total station or GPS to precisely locate and record the coordinates of all existing manhole positions along the existing roadway before excavating the subgrade.
 
1.4 Layout of the cement-stabilized crushed stone subbase
 
During the construction of the cement-stabilized subbase, surveying can still be carried out using elevation reference lines established at the edge stakes on both sides of the roadway. Survey personnel must also conduct random checks at all times to prevent errors. Since the installation of the curbstone foundation will follow the completion of the cement-stabilized subbase, it is essential to ensure that the curbstone foundation is constructed to the specified thickness. To this end, during the construction of the cement-stabilized subbase, the elevation of the roadway edge line must be accurately controlled and maintained in accordance with the design.
 
1.5 Layout for the Construction of Side Curb Stones
 
Due to the increased precision requirements for curb stones, this step must be carried out using a total station or a theodolite for edge-line surveying.
 
1) Straight-line segments. Due to errors in surveying instruments, setting-out data, and stakeout operations, points laid out on the ground along what is intended to be a straight line on the plan generally do not lie precisely on that same line. Therefore, it is necessary to establish a straight line—using stringing—that passes through as many temporary stakes as possible or comes as close as possible to them. Stringing can be carried out using a total station or a theodolite; finally, two or more control stakes are driven at points A and B or along the line connecting them, thereby fixing the straight line on the ground. When using a total station or a theodolite for stringing, the instrument may be set up at point A, aimed at point B to establish the direction, and then stringing and stakeout can proceed. For straight-line layout without special requirements, one stake should be set out every 20 meters, and the top elevation of the curbstone should also be marked on each stake.
 
 
2) Curved Section: After calculating the coordinates of each stake along the curve, use a total station to set out stakes at 10-meter intervals. Similarly, the top elevation of the curbstone shall be marked on each stake.
 
1.6 Layout for Construction of the Cement-Stabilized Base Layer
 
At this stage of construction, the curb stones along the roadway have been fully installed and the road alignment has been essentially finalized; therefore, alignment control is no longer required for the cement-stabilized base course, and only elevation control is necessary. Since pavers are now being used to place the cement-stabilized base course, elevation control is predominantly implemented using the string-line method. The string-line method involves setting out the road elevations at designated stake locations—based on chainage and the transverse slope of the string line—on fixed reinforcing bars or aluminum alloy guide rails. During construction, surveyors must still conduct random checks of the centerline elevations to prevent errors.
 
1.7 Layout for Asphalt Pavement Construction
 
Prior to asphalt paving, the paver’s paving width shall be determined in advance, sideline markers shall be laid out according to this width, and the cross-sectional profile of the cement-stabilized crushed stone base shall be surveyed. The pavement surface elevation shall then be compared with the design elevation, and the paver settings—such as superelevation and midline elevation—shall be adjusted as necessary to ensure accurate paving.
 
2 Construction Surveying for Drainage Works
 
Accurately setting out drainage works such as pipes and trenches in accordance with the design drawings is a crucial component of drainage surveying. The accuracy of construction staking directly affects both the project schedule and quality. Therefore, surveyors must carefully study the drawings, meticulously verify the elevations of all dimensional details, and fully understand the design intent to ensure timely and precise surveying. In addition to completing standard preparatory work, construction surveying for drainage projects also requires checking and re-verifying the plan positions and elevations of existing pipe and trench outlets as well as other above- and below-ground structures that intersect with the pipeline. If discrepancies are found between the field measurements and the design data, or if any other issues arise, they must be promptly coordinated with the design authority for resolution.
 
2.1 Determination of the Pipeline Centerline
 
All pipeline works for new construction projects shall be determined in accordance with the road design standard cross-sectional and plan views. Surveyors shall first ascertain the relationship between the pipeline centerline and the road centerline, and then stake out the pipeline centerline based on the road centerline. When establishing the pipeline centerline, center stakes shall be set at the pipeline’s starting point, ending point, planar inflection points, control points along straight sections, inspection wells, and other such locations as indicated in the design drawings; in addition, construction control stakes shall be placed at appropriate locations outside the trench excavation boundaries at these points.
 
2.2 Ascertain the Actual On-Site Conditions
 
1) After the design institute hands over the stakeout control benchmarks, use a level to measure the elevation of the upstream and downstream pipeline connection points and verify whether they match the design elevations. If there is a discrepancy, prepare written documentation and submit it to the owner and the design institute (and, once the change is confirmed, promptly request the official written approval).
 
2) Prior to excavation, after staking out the pipeline opening lines, excavate trial pits along the pipeline route in accordance with the on-site pipeline handover documents organized by the Employer (which fall within the scope of variation orders and require quantity verification by the Supervision). Once the existing underground pipelines within the road right-of-way have been exposed, mark their manhole locations, materials, burial depths, orientations, types, and other relevant attributes on the drawings by location, and prepare a corresponding tabular summary.
 
2.3 Determining the Groove Edge Line
 
After staking out the pipeline centerline, determine the width of the trench opening at the top based on the excavation depth, and then stake out the excavation boundary lines on both sides. If the working face does not permit the specified opening width, other construction methods shall be determined in accordance with actual conditions and in consultation with the Employer, the Supervising Engineer, and the Designer; construction may proceed only after the relevant specialized construction plan has been finalized.
 
2.4 Compare the on-site measured results with the drawings.
 
Measure the in-situ elevation at each pipeline excavation location according to the stakeout coordinates, and compare the actual excavation depth with the design drawing’s specified excavation depth. If there is a significant discrepancy, potential causes include errors in benchmark settings, field measurement errors, drawing errors, or deviations between the actual site conditions and the design. In such cases, a thorough, item-by-item inspection should be conducted immediately to prevent major mistakes.
 
2.5 Precautions for Surveying During Construction
 
1) During pipeline excavation, surveyors must use a level to continuously monitor and measure the entire trench profile; it is strictly prohibited to drive wooden stakes in advance and then delegate elevation control to other personnel.
 
2) Upon commencement of trench excavation, first determine the approximate excavation depth based on the preliminary survey results. When the excavation reaches approximately 30 cm above the design invert elevation of the pipeline structure, stop excavating. Then, excavate upward from the pipe invert elevation (at the water surface) by 1 m (the uplift height may be adjusted as needed based on site conditions). Install leveling stakes along both sides of the trench. To ensure adequate compaction at the trench bottom, do not use mechanical equipment to excavate directly down to the pipeline structure’s base; instead, leave a 20-cm layer and excavate this remaining portion manually, following the level of the stakes, adding the pipe wall thickness, and then manually finish and level the trench bottom. During trench excavation, continuously verify and re-measure the trench alignment using roadside stakeout points to prevent any deviation in the trench’s position.
 
3) After completion of the pipeline trench, use surveying instruments to re-establish the centerline at the trench bottom and, along the centerline, stake out the elevations corresponding to each station. At each manhole location, install additional elevation stakes to control the elevation of the manhole bottom.
 
2.6 Key Points for Caisson Surveying and Construction
 
Caisson sinking control:
 
1) During the sinking of the well casing, tilting is highly likely to occur and must be closely monitored. Even under poor soil conditions and as the casing approaches the design elevation, there remains a risk of tilting. Therefore, continuous surveying and timely correction are essential.
 
2) There are numerous reasons for tilting during the sinking of the wellbore, primarily due to uneven soil conditions beneath the cutting edge at the bottom of the wellbore, imbalanced earth pressures around the well wall, asymmetrical excavation practices, and the presence of obstacles at a specific location beneath the cutting edge.
 
3) The top-down measurement method is generally used to monitor wellbore inclination: a level is employed to measure the elevations of several fixed points along the upper edge of the wellbore, and the wellbore’s degree of inclination is calculated based on the elevation differences. Subsequently, effective corrective measures are implemented to rectify the deviation.
 
4) As the caisson approaches the design elevation, the frequency of monitoring shall be increased. To prevent excessively rapid self-sinking, the soil at the cutting edge may be left in place; however, once the caisson has reached the design elevation, the bottom shall be sealed immediately.

11